Tuesday, July 31, 2007

Chain Link Fence to be Installed!

The next sign that construction is imminent at the Library will be the installation of a chain link fence across the parking lot. The fence will separate the Library and its activities from the construction site excavation that will soon be underway. Parking will be severely cut and the stair way to the park, proper will be fenced off. Parking in the Library lot will be strictly limited to those using the Library; one hour parking will be enforced.

Friday, July 27, 2007

Library to Close for one Day- Monday, July 30th

Just for one day - the Library, the entrance, the parking lot- all will be closed for the day so that contractors can begin site work. All of the trees that need to be cut down for both the building expansion and the parking space increases will be taken down on that one day. We apologize for the inconvenience, and of course, no fines will be charged for materials due that day that are returned a day late. Our intent is to close ONLY when the contractors determine that conditions are unsafe for the public - we hope that there are very few days in the next 18 months for which this is the case!

Wednesday, July 25, 2007

Construction Progress Report

The modular is gone, the construction trailer is here, and the week of July 30th will see trees removed so that construction can begin. Be prepared to see a few large trees taken down so that the Library can expand. We will all greet this event with mixed feelings. As soon as we know which day the tree removal will take place, we will post it here and on our home page. The Library parking lot will be closed that day.

Friday, July 20, 2007

Construction Trailer Arriving at Library

On Tuesday, July 24th, the Contractor’s Construction Trailer will be delivered and situated on the South side of the Library property along Pleasantville Road. This will necessitate some closing of the Library entry and parking lot. If you visit, you may want to park at Atria and walk through Law Park in order to avoid delays. Unfortunately, we do not know what time the 40’ trailer will be delivered.

Monday, July 16, 2007

Ground Breaking July 27-10:00 am

A ceremonial ground breaking will be hosted by the Village and Library Boards at the site of the new construction on Friday, July 27th at 10:00 am. Join us for a few words of inspiration and some lemonade and cookies!

Modular to be Removed, Wednesday, July 18th

The Library Modular, which has served as the Children’s room for the past three years, will be removed from the Library this Wednesday, July 18th. While the Library will be open for business, parking will be limited and the parking lot may be closed when the modular is ready to roll out onto Pleasantville Road. In consideration of safety and noise, we have cancelled all Library programs previously scheduled for that day. The Modular will be moved to the DPW site and become office space for the Department of Public Works.
The following week (day to-be-announced) site work will begin with the removal of some trees and the placement of the Construction trailer. Although none of us like to see trees taken down, it is a necessary step toward expanding the Library. The site plan was carefully reviewed by the Village Planning Board and adopted by the Village Board.